Construction Progress

19.11.2024 • Final Finishes

19.11.2024 • Final Finishes

19.11.2024 • Final Finishes

19.11.2024 • Final Finishes

22.10.2024 • Marble Staircase Installation

22.10.2024 • Kitchen Installation

22.10.2024 • Graffiato & Aluminium Installation

22.10.2024 • Graffiato & Aluminium Installation

22.10.2024 • Graffiato & Aluminium Installation

09.10.2024 • Water Heaters & Tanks

19.08.2024 • Insulation

19.08.2024 • Insulation

19.08.2024 • Hot Water Supply System

09.07.2024 • Roof Garden Structure Completion

28.06.2024 • Second Floor Brickwork

28.06.2024 • Second Floor Brickwork

28.05.2024 • Second Floor Slab

14.05.2024 • Second Floor Columns

14.05.2024 • Parking Brickwork

14.05.2024 • Parking Brickwork

14.05.2024 • Parking Brickwork

24.04.2024 • Parking First Aid

24.04.2024 • Parking First Aid

23.04.2024 • First Floor Slab

15.04.2024 • First Floor Columns

04.04.2024 • Parking Slab

04.04.2024 • Parking Slab

19.03.2024 • Parking Slab

11.03.2024 • Foundation